ANALISIS PERBANDINGAN BIAYA DAN WAKTU PELAKSANAAN FONDASI TIANG BOR DAN TIANG PANCANG (Studi Kasus Gedung Sekolah SMU Taruna Nusantara di Cimahi, Jawa Barat)

Rosyadi, Ashari (2025) ANALISIS PERBANDINGAN BIAYA DAN WAKTU PELAKSANAAN FONDASI TIANG BOR DAN TIANG PANCANG (Studi Kasus Gedung Sekolah SMU Taruna Nusantara di Cimahi, Jawa Barat). Undergraduate thesis, Universitas 17 Agustus 1945 Semarang.

[thumbnail of REPOSITORY, Ashari Rosyadi, 241003222012002, RPL - ashari rosyadi.pdf] Text
REPOSITORY, Ashari Rosyadi, 241003222012002, RPL - ashari rosyadi.pdf

Download (2MB)
[thumbnail of ashari rosyadi-lembar konsultasi.pdf] Text
ashari rosyadi-lembar konsultasi.pdf

Download (262kB)

Abstract

ABSTRAK

Fondasi adalah bagian struktur dari sebuah bangunan yang memiliki peran sangat penting yaitu menopang beban bangunan diatasnya dan menyalurkannnya ke tanah. Pada umumnya dalam
perencanaan dan pelaksanaan sebuah proyek konstruksi khusunya bangunan gedung dipilih satu jenis fondasi dalam baik itu fondasi tiang pancang atau tiang bor, untuk mempermudah pelaksanaan fondasi dalam dan efisiensi sumber daya yang diperlukan. Pada studi kasus pembangunan Gedung Sekolah SMU Taruna Nusantara di Cimahi, Jawa Barat ini, pelaksanaan awal menggunakan jenis fondasi dalam yaitu jenis fondasi tiang pancang. Penelitian yang akan dilakukan adalah menganalisis
jika seluruh fondasi dalam pada bangunan ini dicoba direncanakan dengan menggunakan fondasi bore pile. Perubahan yang akan dilakukan adalah mengganti fondasi dalam di bawah pile cap yang semula menggunakan tiang pancang. Hasil analisis yang akan disajikan adalah perbandingan antara fondasi tiang pancang dengan tiang bor dari segi waktu pelaksanaan dan biaya yang dibutuhkan. Biaya pelaksanaan fondasi tiang bor Rp 426.307.277,13.(Empat ratus dua puluh enam juta tiga ratus
tujuh ribu dua ratus tujuh puluh tujuh koma tiga belas rupiah). Selanjutnya untuk biaya pelaksanaan fondasi tiang pancang Rp 638.946.741,30.(Enam ratus tiga puluh delapan juta sembilan ratus empat puluh enam ribu tujuh ratus empat puluh satu koma tiga puluh rupiah). Biaya pelaksanaan fondasi tiang bor lebih ekonomis 33,28% dibandingkan dengan biaya pelaksanaan fondasi tiang pancang. Waktu pelaksanaan fondasi tiang bor adalah 11 hari kerja dan pengujian tes PDA dihari ke-18 minggu ke-3 atau setelah tiang bor pertama umur 14 hari. Selanjutnya untuk waktu pelaksanaan fondasi tiang pancang adalah 17 hari kerja dan pengujian tes PDA bisa langsung dihari ke-1 minggu ke-1. Faktor yang mempengaruhi perbedaan biaya dan waktu pelaksanaan fondasi tiang bor dan tiang pancang adalah daya dukung tiang izin, jumlah fondasi tiang bor dibanding fondasi tiang pancang, item pekerjaan, waktu sewa alat, dan waktu tunggu tes PDA.

Kata kunci: Fondasi, Tiang Bor, Tiang Pancang, Biaya, Waktu.

===============================================================

ABSTRACT

A foundation is a structural component of a building that plays a crucial role in supporting the load of the building above it and transmitting it to the ground. Generally, in the planning and implementation of a construction project, particularly for buildings, a single deep foundation type, either a pile foundation or a bored pile foundation, is chosen to simplify the implementation and to streamline the required resources. In this case study of the construction of the Taruna Nusantara
High School Building in Cimahi, West Java, the initial implementation used a deep foundation type, namely a bored pile foundation. The research will analyze if all the deep foundations in this building are designed using a bored pile foundation. The change that will be made is replacing the deep
foundation under the pile cap, which originally used bored piles. The results of the analysis that will be presented are a comparison between pile foundations and bored piles in terms of implementation time and costs. The cost of implementing the bored pile foundation is Rp. 426,307,277.13. (Four hundred twenty six million three hundred seven thousand two hundred seventy seven point thirteen rupiah). Furthermore, the cost of implementing the pile foundation is Rp. 638,946,741.30. (Six
hundred thirty eight million nine hundred forty six thousand seven hundred forty one point thirty rupiah). The cost of implementing the bored pile foundation is 33.28% more economical compared to the cost of implementing the pile foundation. The implementation time for the bored pile
foundation is 11 working days and the PDA test is on the 18th day of the 3rd week or after the first bored pile is 14 days old. Furthermore, the implementation time for pile foundation is 17 working days and PDA test can be done directly on the 1st day of the 1st week. Factors that influence the difference in cost and implementation time for bored pile foundation and pile foundation are the permitted pile bearing capacity, the number of bored pile foundation compared to pile foundation, work items, equipment rental time, and PDA test waiting time.

Keywords: Foundation, Bored Piles, Piling, Cost, Time.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Fondasi, Tiang Bor, Tiang Pancang, Biaya, Waktu
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD28 Management. Industrial Management
T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction
Divisions: Fakultas Teknik > 22201 - S1 Teknik Sipil
Depositing User: Fakultas Teknik
Date Deposited: 28 Aug 2025 07:19
Last Modified: 24 Dec 2025 03:16
URI: http://repository.untagsmg.ac.id/id/eprint/2272

Actions (login required)

View Item
View Item